Tuesday, November 3, 2015

Wednesday, November 24, 2010

Another great workday!

We had another productive day building trail today. We were able to clear another good length of trail...the beginner trail is almost complete! Special thanks to everyone who came out to help!

Tuesday, November 23, 2010

Trail building day one update...

We had a good crew of 8 people come and help start clearing the trail. Had a nice sunny cool day to work! Over 1 mile of trail has been cleared! The 1/2 mile accessible/nature trail is mowed and brush is trimmed back, and more than half of the beginner mtn bike/hiking trail is cleared. Hoping to get at least a 1/2 day of more work done tomorrow!

Field trail clearing


Katherine and Greg clearing the path for the accessible trail.

Clearing trail


the initial first pass with the "billy goat" brush mower

Monday, November 22, 2010

Trail work day(s) update...

The latest forecast update from the National Weather Service says decreasing clouds Tuesday, with temps dropping to low 40s by late afternoon...that's not too bad! For Wednesday it looks like we might get a 1/2 day before the rain moves in after noon.

I am picking up the brush mower at 7am, so I should be out at the trails area a little before 8am.
Tom's bringing coffee, and I have bagels.

Questions? feel free to give me a call at 273-4934

-Kyle

Saturday, November 13, 2010

Welcome to the Prairie Creek Trails Project

We will post pictures, project status and upcoming trail building events here!